# The relative scheduling of tasks in the checklist template

# The relative plan of the tasks in the checklist template

## Only the model moderators are authorized to modify the model tasks.

There is always a reference date for a checklist. For example, for the welcome of a new employee, the reference date is the someday when the new employee takes up his or her position. So there will be tasks to be done before, during and after the someday. This is what we call relative planning; D-30, D0, D+90, etc.

To configure the relative dates of the tasks in a checklist template :

1.  Click on the **template** in question
    
2.  Click on the button with the **three vertical points**
    
3.  Click on **Edit Template Tasks**
    

![](https://downloads.intercomcdn.com/i/o/173680271/192e009b6527696fd76e881b/1-modfier-les-taches-du-modele.png)

It is also possible to define relative dates when creating the template when entering tasks.

## Examples of relative plan

It is possible to set the planned dates and due dates for the model tasks so that they are effective for all future checklists. Here are some examples to understand this use case:

The task "_Get signature on work contract_" should always be done 30 _days before the employee joins the company_. To configure the task in question :

1.  Click on the task, the details pane opens on the right side of the screen.
    
2.  Click on the **drop-down menu** under the _Planned date_ field, select **Planned date X days before the reference date**.
    
3.  Enter the desired number of days for the relative plan, here _30 days before the reference date_.
    

![](https://downloads.intercomcdn.com/i/o/173680330/d63dce1f64f52ade65b8538f/2-planifier-30-jours-avant-la-date-de-reference.png)

It is possible to proceed in the same way if it is necessary to define due dates for the completion of the tasks. To do so, proceed in the same way as for the planned date configuration, this time setting the **Due date** field.

![](https://downloads.intercomcdn.com/i/o/173680380/d7d36ad26edd3ec80644844f/3-planifier-echeance-30-jours-avant-la-date-de-reference.png)

The task _Welcome at the reception_ desk should always be performed _on the D-day_. To configure the task in question :

1.  Click on **the task**, the details pane opens on the right side of the screen.
    
2.  Click on the **drop-down menu** below the _Planned date_ field, select _Planned date at reference date_
    

![](https://downloads.intercomcdn.com/i/o/173680391/f4a0a2106f2ced9acc8439b7/4-planifier-a-la-date-de-reference.png)

It is possible to proceed in the same way if it is necessary to define due dates for the completion of the tasks. To do so, proceed in the same way as for the planned date configuration, this time setting the **Due date** field.

![](https://downloads.intercomcdn.com/i/o/173680412/416c6f75677900f1db491881/5-planifier-echeance-a-la-date-de-reference.png)

And finally, the task _Fixing an appointment for the evaluation at the end of the trial period_ must always be performed 90 days after the employee has started work. To configure the task in question :

1.  Click on **the task**, the details pane opens on the right side of the screen.
    
2.  Click on the **drop-down menu** below the **Planned date** field and select **Planned date X days after reference**
    
3.  Enter the desired number of days for the relative plan, here _90 days after the reference date_
    

![](https://downloads.intercomcdn.com/i/o/173680423/714345bf7c3d47283f8131ac/6-planifier-90-jours-apr%C3%A8s-la-date-de-reference.png)

It is possible to proceed in the same way if it is necessary to define due dates for the completion of the tasks. To do so, proceed in the same way as for the planned date configuration, this time setting the **Due date** field.

![](https://downloads.intercomcdn.com/i/o/173680446/2d363e3990c79d7e274003db/7-planifier-echeance-90-jours-apr%C3%A8s-la-date-de-reference.png)